- Home
- Government
- Departments
- Engineering Division
- Construction Project Updates
Construction Project Updates
City of Twinsburg
SUM-Ravenna/Shepard/Broadway/Richmond Intersection Improvements, Phase 2, PID 113165
Twinsburg, Glenwillow, Macedonia, Oakwood Village, Ohio
Public Notice and Comment Period
The City of Twinsburg, in partnership with Glenwillow, Macedonia, and Oakwood Village, is planning improvements to the Ravenna/Shepard/Broadway/Richmond Intersection. This federally funded project will improve safety and functionality of the intersection by adding right-turn lanes on Ravenna Road and Broadway Avenue, and a left turn lane on Shepard Road. The work will also include curb, sidewalk, signal, limited driveway restoration, and drainage improvements. The proposed project will include the acquisition of minor new permanent and/or temporary rights-of-way as necessary to accommodate the proposed work.
A minimum of one lane of traffic in each direction for all roads will be maintained during the duration of construction and local access for abutting properties and adjacent streets will be maintained at all times. Construction and lane restrictions will be posted prior to the start of construction. The project is currently in preliminary development and work is anticipated to begin in 2025. The estimated construction cost of the project is $3,300,000.00.
The project will not result in any substantial impacts to environmental resources. The environmental review, consultation and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding, dated June 6, 2018, and executed by FHWA and ODOT.
The City of Twinsburg is requesting that any comments you may have regarding the proposed project and/or environmental impacts be submitted by September 30, 2022 to:
Ms. Amy Mohr, P.E., City Engineer
City of Twinsburg Engineering Division
10075 Ravenna Road, Twinsburg, Ohio 44087
330-963-6233
For Further project information go to the City of Twinsburg, and/or Glenwillow, Macedonia, and Oakwood Village websites:
2023 Road Improvements Project with Water Park Concrete Repair, Glen Meadow Park Parking, Pickle Ball Court Resurfacing and Sidewalks
The annual road program is a maintenance program providing overlays to extend the life of the pavement. The work for this project generally includes asphalt resurfacing, asphalt repairs, concrete curb removal & replacement, asphalt grinding, on minor/major asphalt repairs, curb and sidewalk repairs, catch basin repairs and miscellaneous other repairs.
2023 Project will Include resurfacing of Neille Ln, Adam Run, Jason Dr, portions of Waldo Way, Gill Ct, Patton Ct, portions of Bridget Ln, portions of Andrew Dr, Deerfield Ct, Heron Cv, Mallard Cv, portions of Belmeadow Dr, Iris Glen Dr, and Enterprise Pkwy. The outdoor pool will have concrete deck repairs, Glen Meadow Park Parking area to have repairs and be sealed, resurfacing of the Pickle Ball Courts, resurfacing of the basketball court and asphalt pad for Safety Town. Miscellaneous sidewalk repairs and patching per the bid documents. . City retains the right to adjust their order without any liability, after this project is awarded by City Council.
Block 1: Glen Meadow Park & Water Park - Saw cutting, removal and replacement of concrete within the water park. Saw cuts required to remove existing panels designated for replacement must not extend into adjacent panels. This work can begin in April as weather allows as is required to be complete May 5th in order for the water park to be open on time for the 2023 season. Glen Meadow Park items (Alternates 3-5 and Base Bid Item 64) may begin concurrently with or following Water Park repairs. The Glen Meadow Parking Lot Repairs must be completed prior to May 25th.
Block 2: Sidewalks & Glenwood Dr Catch Basins -Saw cutting, removal and replacement of concrete sidewalk, selective tree root pruning at trip hazards and utility adjustments in locations designated on SIDEWALK TABLE. This work can begin in April as weather allows.
Block 3: Neille, Adam, Jason - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. This work can begin in April as weather allows and will be completed by October. Street Resurfacing Location Map
Block 4: Portion of Waldo Way, Gill Court, Patton Court, Portions of Bridget & Andrew - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. This work can begin in April as weather allows and will be completed by October.
Block 5: Portion of Belmeadow, Deerfield, Heron (Alternate 1 Bid), Mallard (Alternate 2 Bid) - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. This work can begin in April as weather allows and will be completed by October.
Block 6: Iris Glen and Enterprise - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. This work can begin in April as weather allows and will be completed by October.
Block 7: Miscellaneous Repairs - Perform catch basin adjustment and asphalt pavement milling and paving to provide positive drainage at 8400 Darrow Road. Miscellaneous pavement patching repairs as indicated in Table 1. This work can begin in April as weather allows and will be completed by October.
2023 Road Striping Program
2023 Cannon Road Resurfacing
The work included in this project generally includes asphalt grinding involving re-profiling to obtaining minimum cross slope, resurfacing, asphalt base repairs, storm basins being adjusted or replaced and replacement of pavement markings on Cannon Road. This work will take place between Liberty Road and Ravenna Road. Butt joints at intersecting streets have various offsets from the centerline of Cannon Road.
Work for this project shall begin on June 20, 2023 and be completed by August 11, 2022. Message Boards & Signage are to be installed by June 5th to provide a two-week advance notification to the traveling public. No work will be performed July 4th – July 12th.
The City has the right to award this project to the lowest, competent and most responsible bidder.
2023 Dooridge Drive Improvements
The work included in this project generally includes replacement of existing sanitary sewer, including service connections with new cleanouts, installation of 8” water main, line valves, new hydrant assemblies and water service connections, storm sewer replacement and repairs, new asphalt pavement over cement stabilized sub-grade, concrete aprons and sidewalk repairs, including lawn restoration on Dooridge Drive. All proposed work shall meet all City, EPA and CWD requirements and ordinances of which the Contractor must become familiar with. Various improvements shown on plans are approximate only which the contractor shall verify location and elevation before installing. All new/replacement sanitary service/storm connections will have a cleanout installed near the right of way line or as directed. Contractor shall use all available resources in protecting and supporting the existing storm sewer, water line and utility poles at all times, especially during excavation.
Construction work begins on February 13, 2023 and must be completed by August 27, 2023.
The City has the right to award this project to the lowest, competent and most responsible bidder.
2023 Ravenna Road & Town Center Improvements
The work included in this project generally includes the removal and replacement of the existing sanitary sewer on Ravenna Road, between Darrow Road (SR91) to East Aurora Road. Work includes sanitary main line and sanitary manhole replacement, service laterals including cleanouts, impacted storm sewers and appurtenances, asphalt pavement resurfacing, concrete apron replacements, sidewalk replacements, traffic striping, lawn restoration and miscellaneous repairs and improvements. The project also includes replacing approximately 146 linear feet of 8" sanitary in easement of E. Aurora Road between Buildings MH to MH and repair pavement.
One lane in each direction on Ravenna Road to provide access to all businesses must be open at all times.
The City has the right to award this project to the lowest, competent and most responsible bidder.
Ravenna Road-Twinsburg Township
Summit County Engineers Office will be working on resurfacing Ravenna Road in Twinsburg Township limits. The project includes culvert replacement which will require a 2 week estimated closure. Traffic will be maintained during resurfacing. Estimated sale date 3/8/2022 Construction start 6/1/2022.
This Detour will utilize Old Mill Road and SR 91 – Darrow Road.
Alan Brubaker, P.E., P.S.
SUMMIT COUNTY ENGINEER
538 E. South Street
Akron, Ohio 44311
Tel: 330-643-5269
Private Development
If you have concerns about an existing street tree please contact the Service Department Arborist for a tree inspection to determine status of tree. Windsor Way is scheduled for Ash Tree removal and replacement as part of the 2022 Tree program. The City continues to monitor the health of Ash in the City Right of Way and schedules removal/replacement as necessary.