Construction Project Updates

 

2018 Joann & Lila Place Reconstruction Project Including Terrace Drive Resurfacing

Construction:  March 2018 - August 2018
Contractor:  Lockhart Concrete Company
Amount:  $ 1,080,334.75

This project is the reconstruction of Joann Place and Lila Place including sanitary and storm sewer replacement.  Construction generally includes removal of the roadway and replacement with concrete curb, 6” curb drain, full depth asphalt pavement over cement stabilized sub-grade, storm sewer/storm lateral replacement, storm basins, sanitary sewer/sanitary lateral replacement, concrete aprons replaced, lawn restoration and miscellaneous other improvements.  Additional storm sewer catch basins and sewers are also being considered to address rear yard drainage on Joanne Place.  A storm culvert on Terrace Drive between Sherwin Drive and Glenwood Drive will be replaced requiring a temporary road closure.  Terrace will then be milled and resurfaced as part of this project.

Construction Notice No. 1 - Lila-Joann
Construction Notice No. 1 - Terrace Dr

SUM/CUY-91-21.65/0.00 - Darrow Rd from Glenwood Drive to Lisa Lane



Contractor:  ODOT Administrated
Anticipated Bid:  1st Half of 2018
Anticipated Construction:  Sept 2018 - Sept 2019

This project consists of combination full depth reconstruction, widening and resurfacing over a length of approximately 0.53 miles along S.R. 91 (Darrow Road) including installation of curbs, sidewalks, and a modern roundabout at the S.R. 91 and Meadowood Blvd. / Ethan’s Drive intersection.

Prior to the widening contract starting, private utilities must first be relocated:

*Dominion Gas Relocation Project
DOMINION GAS began work on 2/15/18.
        New gas line will be installed on the west side of S.R. 91 from Glenwood Drive to Solon Corp. Limits.

*Ohio Edison Pole Relocation Project
Anticipated construction:  April – August, 2018 (Includes all utilities co-located on poles)


2018 City-Wide Sidewalk Program

Construction:  May 2018 July 2018
Contractor:  Spano Brothers Construction Co., Inc.
Amount:  $ 88,364.08

The Sidewalk Program replaces sidewalks that have an offset of 1” or more and are determined to be City Responsibility. The City takes responsibility for sidewalk repair for damage associated with City owned utility failures or damage from street tree roots.  To determine City responsibility the Public Works Department performs both a visual inspection and a video/dye testing inspection of the sewers.   After the inspections, the location is determined to either be Home Owner or City Responsibility.  In addition to the replacement program, the Service Dept performs sidewalk concrete leveling city wide throughout the summer months.

The work being performed in 2018 is for the locations determined to be City Responsibility from 2017 inspections. 

If you want to report a sidewalk concern to determine if it is City or Home Owner responsibility please contact the Service Dept at (330) 963-6212.   An inspection will be performed and if determined to be City responsibility, it will be included in future year maintenance programs. 


2018 Road Improvements Project 



Construction:  May 2018 – July 2018
Contractor:  Perrin Asphalt Company
Amount:  $ 1,054,399.30

The annual road program is a maintenance program providing overlays to extend the life of the pavement.  The following streets are included in this year’s program:

Block 1:  Ridgewood Drive, Serene Court, Belfair Drive & Briardale Court: Full width asphalt grinding, concrete base pavement repairs, concrete curb & storm basin repairs, miscellaneous other work and asphalt resurfacing. 

Block 2:  Hermitage Drive: Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs, miscellaneous other work and asphalt resurfacing. 

2018 Roadway Striping Project

Construction:  July 2018
Contractor:  JD Striping & Services, Inc.
Amount:  $ 70,972.05

This project consists of re-painting existing traffic lane lines, stop bars, cross walks, lane arrows, and other pavement markings throughout the City.


2018 City-Wide Tree Planting Program

Planting: 
 March - May and October - December
Contractor:  Vizmeg Landscape, Inc. 
Amount:  $ 78,492.00

The 2018 City-Wide Tree Planting list has been compiled by the Engineering Department and includes new residential developments and replacement trees that have been removed by a City project or as a result of mortality.

If you have a tree lawn tree issue please contact the City arborist through the Service Department 
at (330) 963-6212
.


2018 Darrow Road SR91 Sanitary Sewer Replacement (Ravenna to Tinkers)  


Proposed Construction:   August 2018 – November 2018

The work included in this project generally includes the removal and replacement of the existing sanitary sewer on Darrow Road, S.R. 91, between SR82 and Richner Court. Work includes sanitary mainline, service laterals, manhole replacement, abandonment of existing sewer, asphalt pavement and apron repairs, sidewalk and lawn restoration and miscellaneous other repairs and improvements.

Prior to the construction of the sanitary sewer project, Ohio Edison will be relocating utility poles - anticipated work to occur April-August.

COMMUNITY CONSTRUCTION

Boulder Brook Subdivision
Planning Commission approved a preliminary plat for residential subdivision in R-5 district consisting of 27 lots. Boulder Brook is to be accessed from a cul-de-sac intersecting Darrow Road at Miktarian Memorial Parkway.  All roadways have been installed and Ryan Homes is currently building.

Corbett's
 Farm 

Corbett Farm is a 94 lot single family residential development that started construction in October 2013. Corbett’s farm main entrance is located on Glenwood Drive with roads connecting to Meadowood,, ParkviewCorbett's Lane providing secondary access from both the Meadowood Subdivision and Chestnut Trails Subdivision.  All roadways have been installed and Pulte is currently building.  

Shepard Preserve Subdivision
Residential subdivision consisting of 23 lots.  Construction to begin the week of September 18th, 2017.   Construction access is located between Ledge Road and Park Ledge Drive.
Coblentz Homes is the builder.

Whispering Woods Phase III
A proposed 30 lot residential development that will continue off the end of Merryvale Drive in Whispering Woods Subdivision.  The Preliminary Plat is currently being reviewed by Planning Commission.